Permitting Reform at the 1-Yard Line or the 50-Yard Line?

September 25, 2026

Almost two years after the bipartisan Energy Permitting Reform Act (EPRA) failed to materialize, another Senate-led bipartisan permitting reform bill is coming into view just weeks ahead of the November election. This news has sparked a flurry of rumors and reports about the package’s contents, the timing of a vote on the Senate floor, and the content of outstanding Democratic demands. The latest intel suggests that, despite the Trump Administration’s eleventh-hour pressure campaign for passage before the Senate adjourns until the election, negotiators are taking the long view and keeping bipartisan discussions alive.

As it stands, here are the key provisions we expect to be included in the package, based on many conversations, reporting, and staff briefings this week:

National Environmental Policy Act (NEPA) & National Historic Preservation Act (NHPA) Reform:

Similar to the changes proposed in the House-passed SPEED Act, we expect the bill to limit judicial actions to referring permits back to an agency for review (removing the power to revoke a permit) and reduce the scope of “Major Federal Actions” that trigger NEPA review, excluding projects that receive federal loans and those that do not have a substantial part of the project on federal land.

We also anticipate that the bill will contain the NEPA deadlines proposed under EPRA: two years to complete an Environmental Impact Statement (EIS) and one year to complete an Environmental Assessment (EA). These deadlines will also apply to NHPA review, which is expected to run simultaneously with NEPA review. Furthermore, failure to adhere to these deadlines will serve as evidence for litigation if an agency fails to act in a timely manner.

Shifting State Authority under the Clean Water Act (CWA) & Endangered Species Act (ESA):

We expect Republicans have included their priority to limit Section 401 reviews under the CWA. Section 401 certifications (granted by states, tribes, or local governments) are the first step in the CWA’s two-step process. Possible changes to Section 401 include creating a shot clock on reviews, shifting the burden of proof onto states, and requiring permit conditions to be minimally burdensome. In addition to Section 401 changes, we anticipate changes to the EPA’s authority under Section 404(c), which empowers EPA to restrict areas from dredging or fill, overriding U.S. Army Corps assessments.

We also anticipate that the bill will expand states’ authority under ESA, empowering states to carry out ESA consultations in the place of federal agencies.

Transmission Reform:

We expect proposed transmission reform to fall into categories: (1) Improving grid planning and utilization, and (2) Ratepayer Protection.

  1. Grid Planning: Key provisions related to grid planning include strengthening FERC’s backstop authority, strengthening the existing authority for FERC Order 1920 (long-term interregional and regional planning and cost allocation), requiring FERC to engage in a consolidated planning process that simultaneously accounts for transmission and interconnection needs, boosting interregional coordination, and implementing FERC Order 2222, which directs wholesale markets to accept energy aggregators (aka virtual power plants) as market participants, essential for distributed energy resources to engage in wholesale markets.

    The package is also expected to boost the capacity of existing lines by requiring utilities to adopt grid-enhancing technologies (GETs)/advanced transmission technologies (ATTs) and excluding reconductoring (the process of replacing aging electrical wire with higher capacity and more advanced cables) within existing rights-of-way from NEPA reviews, removing it from the definition of a “Major Federal Action.”

  2. Ratepayer Protection: According to the most recent reporting, language similar to the House-passed Ratepayer Protection Act will be included in the package, directing state energy commissions to consider requiring data centers to cover all grid costs associated with their project. Along with this language, we anticipate that the package will offer clarity on who covers costs caused by data centers, like network upgrades, and increase transparency through required reporting on data center energy use.

Technology Neutral Certainty:

Permit certainty, a must-have for Democratic negotiators, has taken many different forms in the myriad legislative proposals released over the past year. We expect the language in this package to provide strong and enforceable protections for projects on a tech-neutral basis. Specifically, the package is expected to lay out clear criteria for developers to claim an unreasonable delay or discrimination — giving project developers a cause of action to challenge delays by presenting evidence including repeated delays beyond the EIS/EA deadlines, delays responding to non-environmental approvals, and other Administrative actions like agency guidance that blatantly discriminates against particular technologies. The administration’s defense will have the burden of demonstrating, based on actual permit data, that the project(s) in question are not facing an unreasonable delay. Project developers who prevail against the Administration will be entitled to damages covering and even exceeding the costs of the project.

We anticipate that the bill will also stipulate clear criteria for the administration to legally revoke, interfere with, or modify permits, including fraud, illegal activity, or imminent risk. However, if the administration pursues any of these actions but fails to provide sufficient evidence in court, the administration will be prohibited from taking any action to limit the project in the future.

These certainty provisions are expected to go into effect nine months (approximately 280 days) after passage, allowing the Trump Administration sufficient time to prepare and begin processing projects under regular order.

Other Provisions:

  • Address the Rosemont decision to create a clear pathway for depositing mining waste on federal lands.

  • Easier permitting for niche oil and gas issues that have a limited federal nexus.

While conversations, reporting, and staff briefings indicate that a deal is around the corner, the details and contents of the final package remain in flux. In either case, we do not expect the package to reach the Senate floor before the Senate recesses for the November elections. This extended period grants Democrats sufficient time to socialize the bill and denies Republicans a major bipartisan win ahead of the elections. Nonetheless, delaying a vote to the lame-duck session opens up the Senate floor to a vote on the Ratepayer Protection Act next week — a challenging vote for Democrats caught between one of voters’ top priorities, with albeit limited enforceable impact, and delivering Republican Senator Jon Husted (OH) an optical win.